    Retaining Wall without heel and toe

    Limestone can be a bit tricky as it may have voids. Be careful. Suggest you consider post tensioned anchors. DSI (Dywidag) have an excellent system, and as the bars can be spliced easily, and protected from corrosion with their system, should be usable. You may have to have a wall that is thin...
  2. jimbeck

    ecology block retaining walls w/ geogrid

    Cornerstone is at risistone.com, and Allan Block is at allanblock.com They do provide computer programs for their products; but these can be a bit difficult to operate. If used, they should be verified by independent calculations. I have seen reports and design procedures from geotextile...
  3. jimbeck

    Active vs Earth Pressure

    The active pressure is when the wall is allowed to move - agreed; but then in long term retaining walls the soil consolidates and the pressure builds. For walls with a life of less than 1 year (shoring for excavations that will be backfilled), the active pressure can be used. Longer durations...
  4. jimbeck

    ecology block retaining walls w/ geogrid

    The geogrid suppliers have several articles on this subject, showing test results. Cornerstone, Allen Block and others have websites with information.
  5. jimbeck

    Timber Lagging - Long Term Performance

    I have used preserved wood timber lagging on several projects. Design for the at rest pressure, aned all should be well.