Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations cowski on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Recent content by grabens

  1. grabens

    Determining soil properties for pile foundations

    Try the attached. I am a practicing geotech and most of the time we can't get clients to pay for site specific characterization. The attached was produced by ASCE and gives a range of typical values to at least start with. Good...
  2. grabens

    Effect of pre-drilling on the capacity of skin friction piles?

    I agree with oldest guy. I would neglect the skin friction in the zone that was pre-drilled. There will obviously be friction within this zone, but it will be reduced when compared to that of a non pre-drilled layer. I would install a test pile with pre-drilling and load it to see if there...
  3. grabens

    Brithish Virgin Islands Limestone/Drilled Shaft Experience Question?

    Hi Ron, This project is in the research stage. No field or laboratory work has been performed yet. This project is going to be an airport runway extension off the island and out into the Carribean Sea to allow for larger planes to come to the island. Project is estimated to be about $200...
  4. grabens

    Brithish Virgin Islands Limestone/Drilled Shaft Experience Question?

    I am looking at a drilled shaft project in the British Virgin Islands. Rumor has it that the limestone there is very hard and difficult to drill. This is a design/build project and the contractor is concerned about difficult installation of drilled shaft foundations that could result in cost...
  5. grabens

    Rigid Pavements on Expansive Soils

    I am working on a project in Fort Worth, Texas. I am looking for some guidence on how to treat the expansive soils for rigid pavement design. The soils are lean clays to fat clays. PI ranges from 29 to 45 LL ranges from 46 to 62 Percent Swell ranges from 0 to 1.7% Natural moistures are +/-...
  6. grabens

    elastic settlement

    I agree with Ron your soil profile suggests that consolidation settlement needs to be evaluated for this project based upon the foundation size and load. You need to get some samples for consolidation tests too.
  7. grabens

    Pumping subgrade, but passing compaction tests? Help!

    Update - The pumping fill was allowed to sit idle for four days during which we did not receive any additional rainfall. The site was re-proofrolled and the subgrade was observed to be firm and unyielding indicating the stability issue was most likely caused by porewater pressure build up...
  8. grabens

    Pumping subgrade, but passing compaction tests? Help!

    I am working on a site where we are adding several feet of fill material. The underlying soils are saturated clayey sand soils (SC). The fill material is a slightly silty sand (-200=12 to 15%) with a modified proctor of 119 pcf and 11% moisture. We have two feet of fill in above the wet...
  9. grabens

    How to test compaction on sites improved with Class C fly ash?

    The soils on site are clayey sand with about 30 to 35 percent fines passing the No 200 sieve. The Modified proctor values of 129 pcf at 12% moisture. The top 12 inches of the pad need to be compacted to 98% modified proctor MDD. We just just got 23 inches of rainfall in the last 48 hours in...
  10. grabens

    How to test compaction on sites improved with Class C fly ash?

    I am working for the owner by contract. However, both the owner and contractor are working together to meet a 3rd party's contractual deadline.
  11. grabens

    How to test compaction on sites improved with Class C fly ash?

    I am working on a site in the panhandle of Florida. The site soils are clayey sands with about 30 percent passing the No. 200 sieve. We have been getting large amounts of daily rain. The soils have become too saturated to compact. The project is on a strict time line and the weather outlook...
  12. grabens

    Seismic Site Classification

    I'll add, unless you have shallow dense to very dense soils or shallow rock, you will be hard pressed to get a site class better than "D".
  13. grabens

    Seismic Site Classification

    The SPT method can be conservative. If it is border line between a Site Class C and Site Class D, it may be prudent to run a field test such as ReMi or Seismic CPT, etc. to measure shearwave response on the site. If the SPT method is not close to a Site Class C, you are going in the wrong...
  14. grabens

    Estimating settlement induced by embankment fill?

    Thanks Fixed Earth! You are awesome!
  15. grabens

    Estimating settlement induced by embankment fill?

    FixedEarth, Thank you for all of your help! Would you be willing to post a copy of your spreadsheet to play around with? Thanks,

Part and Inventory Search