experienced designers take up the following duration to put a complete plan:
1. Conceptual stage - 90 to 120 days. at this stage coordination with the owner is conducted to establish what they want in the project.
2. Design stage - 60 to 90 days. at this stage the plan should be already frozen...
cracks on cement floor is usual because concrete tends to expand and contract on temperature changes.
1 ponding or install jut sacks is one way to control cracks.
2 you could also install small grooves on the flooring to control the area of cracking.
3 the thickness of the flooring is also a...