Thank you for the post.
I should have explained it more clearly.
We are a millwork manufacturing company. I have created my schedule with all tasks being individual, (handrails, stairs, shutters, etc.,), that have a date at which they must ship to be on-site “just in time”. That date may be...
I have 100+ tasks in my production schedule at any given time. What I would like to do is have a “must finish by” date, but have the tasks move into open gaps in my production schedule. How can I make this happen?
mike